Construction of Katuba substation, including a 120 kV line bay, a 120/15kV-24MVA transformer bay, the transformer itself, 15 kV equipment (feeders) and protections.
Construction of the Kipushi-Katuba line, over 10 km, with pylons and ACSR cables.